Planning Scheme - Amendment GC45

Amendment details

Proposal:

Please Note: Proposal description below describes the amendment at exhibition stage. To verify content of the final approved amendment see the Explanatory Report under the Approval documentation tab below.

Facilitates the delivery of the Melbourne Metro Rail Project.

Amendment status: Finished

Amendment status date: 05/01/2017

Environmental Effects Statement (EES): No

Planning authority contact details:

Minister for Planning

8 Nicholson Street, East Melbourne 3002

(03) 8392 5513

Affected planning schemes

  • Maribyrnong
  • Melbourne
  • Port Phillip
  • Stonnington

Amendment stages

Amendment documents

If submissions about an amendment cannot be resolved they will be considered by an independent panel.

  • Date panel requested

    04/01/2016

  • Date panel appointed

    17/08/2016

  • Panel report due date

    05/12/2016

  • Panel chair

    Kathy Mitchell

  • Panel members

    Geoff Underwood (Deputy Chair),Craig Barker,Jenny Donovan,Mandy Elliott,Elizabeth Hui,Helen Lardner,Kate Partenio

View the approved changes to the planning scheme and the amendment documents.

This amendment affects clauses and schedules:

Maribyrnong - Clause 52.03 Schedule, Clause 61.01 Schedule, Clause 81.01 Schedule, Melbourne - (new) Clause 43.02 Schedule 70, Clause 52.03 Schedule, Clause 61.01 Schedule, Clause 66.04 Schedule, Clause 81.01 Schedule, Port Phillip - (new) Clause 43.02 Schedule 31, Clause 52.03 Schedule, Clause 61.01 Schedule, Clause 66.04 Schedule, Clause 81.01 Schedule, Stonnington - (new) Clause 43.02 Schedule 20, Clause 52.03 Schedule, Clause 61.01 Schedule, Clause 66.04 Schedule, Clause 81.01 Schedule,

This amendment affects maps:

Melbourne - 4DDOPT1, 5DDOPT1, 8DDOPT1, 11DDOPT1, Port Phillip - 4DDO, Stonnington - 1DDO

Back to top